|

JOHN
THOMPSON, the Desalination Companys general manager
at the Point Lisas plant this week.
Photo: Adrian Boodan
The
Desalination Company is giving consideration to an Initial
Public Offering of shares on the local stock market.
Unlike many companies that look to the equity market for capital,
Desalcott is not now profitable, said John Thompson, the companys
general manager.
Pointing to the fact that the company has a 20-year contract
with WASA, Thompson said using a conservative approach it
may take getting towards 10 years to make us profitable.
While there may be little prospect of a return on investment
within 10 years, Thompson said the rate of return over the
life of the contract was reasonable.
At
this moment in time, we are not profitable but in the future
we expect to become profitable as we pay down our current
loans.
Desalcott makes operational profit (revenues exceed expenditure)
but not net profit, because it carries a heavy debt load.
Desalcotts main banker is Republic Bank, which had provided
bridging finance for the company.
Last July, Republic provided Desalcott with long-term financing
in the form of a US$112.7 million 20-year loan (its
not a bond, Thompson notes).
Interest on the loan, which was divided into US and TT dollar
tranches, has been fixed for five years. For each subsequent
five-year period, the rate is refixed. The company has a guarantee
that the renegotiated price will be within a certain range,
Thompson said.
Thompson declined to disclose the interest rate being charged
by Republic Bank, stating, Im not sure Republic
would like me to quote it in the newspaper.
In terms of timing, Thompson said the company was looking
at an IPO early next year.
The company might have come to market earlier, but it was
in the process of ramping up production from 22 million imperial
gallons a day, he added. It goes to 24 million gallons later
this month and then to 27.6 million gallons next month.
We
suspect that some of the bigger investors would want to see
that the expanded plant works well. We think that by next
year we should be able to demonstrate that we have an existing
plant that works well.
Desalcott is 60 per cent-owned by local contractor Hafeez
Karamath, whose foreign joint venture partner is US-based
Ionics, a water treatment company.
It is too early to say by how much the partners might sell
down, says Thompson. He said, however, he would imagine
that the new shareholders would have more shares than the
existing shareholders.
Thompson was reluctant to disclose the exact amount of money
Desalcott hopes to raise from the IPO.
He did disclose that the companys current equity is
the equivalent of US$20 million, adding that he hoped the
IPO would be at least that.
So, is the IPO meant to raise capital to reduce some of the
companys debt?
Thats
one possibility, said Thompson, helpfully adding that
the other possibility is that our two existing shareholders
are probably keen to reduce their shareholdings.
Both Ionics and Karamath want to reduce their shareholding
in Desalcott because they want to free up some capital
to move forward and do other development projects.
One of the reasons the company is not more solvent is because
the plant cost more than the initial investors expected to
build.
The Point Lisas site required more civil work which, along
with delays in construction, pushed the total funding requirement
up by 25 per cent.
The
funding (and I dont want to hoodwink you here when I
say funding, this was how much had to be raised to cover everything)
went up from US$120 million to US$150 million.
The
engineering, procurement and construction (EPC) cost went
from US$86 million to US$115.7 million.
The longer construction time and the higher costs would have
wreaked havoc with the initial projections, Thompson agrees.
Yes.
It was a good job interest rates came down.
Delays in completing the construction of the plant did not
only add substantial costs to it, it also led to claims by
WASA that desalcott owes the utility liquidated damages.
The matter of liquidated damages is still to be sorted out
and after going off the record briefly, Thompson said, Desalcott
feels it was not at fault for the delay.
Contract
above reproach
Desalcott is one of several projects undertaken by the former
UNC administration which were beset with allegations of corruption
and favouritism.
Comparing Desalcott to InnCogen and the airport, Thompson
said that unlike those projects, the desalination project
went through a full bidding process.
An invitation to prequalify was issued. Three bids were submitted
and evaluated by a 12-member committee. Desalcott was adjudged
the winning bid.
The bidding process is above reproach, says Thompson.
My
understanding is that there has been talk of an investigation
for in excess of 18 months now. And I dont know if ever,
formally, the investigation will be said to have been completed.
Water price competitive
The price of water sold by Desalcott to WASA is globally competitive,
says John Thompson, especially when the very high quality
of the Point Lisas plant is taken into consideration.
In 2000, Barbados commissioned a desalination plant, which
is being operated by Ionics, the same company which partnered
with Karamath to build the Point Lisas plant.
The local plant, which will be capable of producing 55,000
cubic metres of water, cost about US$120 million to build.
The Barbados plant, with a rated capacity of 30,000 cubic
metres, cost US$12 million.
Asked to compare the T&T plant with a similar plant in
Barbados, Thompson said that the Barbados plant took in brackish
water with about 1,000 parts per million of dissolved impurities.
The Barbados plant takes in water that has been naturally
filtered by coral.
The T&T plant takes in sea water with about 30,000 parts
per million of impurities. The local plant needs extensive
pre-treatment to remove suspended solids in the
water.
The reverse osmosis train on the local plant works at 1,000
pounds per square inch. In Barbados, its closer to 250
lbs per sq inch.
The membranes, piping, pressure vessels and pumping at the
T&T plant were all more expensive, said Thompson.
|